Siemens Campus Erlangen Case study

2013 2015 2017 2019 2021 2022 2020 2018 2016 2014 By 2030 Step-by-step construction of the remaining modules 3-8. Development and realization The project timeline The first employees move into Module 1. Contruction starts on the Module 2 buildings. Construction work on Module 2 of Siemens Campus Erlangen is in full swing. Completion of Module 2 with hallmark Reception Building, four more office buildings and three more parking garages. Start of demolition work for Module 2. Award of framework contract and first delivery of office furniture to the eastern part of Module 1. Winner of the architectural competition: KSP Jürgen Engel Architekten. Siemens affirms its commitment to Erlangen. Construction starts on the Module 1 buildings. Module 1 topping out ceremony. Start of demolition work. Contract award and digital laying of the cornerstone for Module 1. Conclusion of the framework agreements with the city and state. Presentation of the architectural competition. 09